The
2003 ITU-T Telecommunication Equipment Resistibility Recommendations
Mick
J. Maytum
Updates
to the 2000 ITU-T equipment recommendations modify longitudinal
testing and add internal and interport tests.
The
International Telecommunication Union Telecommunication Standardization
Sector (ITU-T) prepublished new versions of the K.20, K.21, K.44,
and K.45 resistibility recommendations in July 2003.4 These recommendations
are in force and replace the 2000 issued versions, covered by an
earlier article5. This article is based on this prepublished material,
but correcting some obvious errors (see Conclusions).
The
increased coverage of the new recommendations withdraws four other
ITU-T Recommendations. Recommendations K.156 on remote-feeding systems
and line repeaters and K.177 on power-fed repeaters are both absorbed
into K.45. Recommendation K.228 on ISDN T/S bus equipment is absorbed
into K.21 and K.419 on internal interfaces at telecommunication
centres is absorbed into K.20. Recommendation K.44 picks up the
test circuits from the absorbed recommendations. This article provides
an overview of testing ports connected to symmetric-pair cables.
The
basic document structure remains the same. Recommendation K.44 is
the test-circuit standard. Recommendation K.20 covers equipment
located at a telecommunications center (central office), K.21 covers
equip- ment located at customer premises (subscribers), and K.45
covers access and trunk equipment.
This
article provides an overview of testing ports connected to symmetric-pair
cables.
External-Port Test Circuits
Single-Port
Test Circuits. There are three test circuit configurations
for single-external-port testing: transverse (Figure 1), port-to-ground
(Figure 2), and port-to-external-port
(Figure 3). Powering or auxiliary
equipment or terminations are included in the test circuits as required
to ensure normal system operating levels. Appropriate coupling and
decoupling elements are added to present low- and high-impedance
paths to the test generator current. Any source or termination fed
via a decoupling element can be ignored from the surge dynamics.
Gas discharge tubes (GDTs), metal-oxide varistors (MOVs), and thyristors
are suitable coupling elements that block under normal conditions
and conduct during a voltage surge. When needed, special or agreed
or appropriate primary protection is added to the equipment ports.
 |
| Figure
1. Transverse testing, single external port. R = resistor, G
= ground terminal. |
By
comparison with those in the 2000 resistibility recommendations,
the new test circuit figures provide more information on test setup.
However, because of this, and because of the need to provide additional
test options, the new test circuits appear more complex.
Transverse
Test Circuit. Transverse testing is carried out with some
untested ports of each type powered or terminated. The unused ports
are left floating. Testing is carried out on both port terminals.
Transverse testing uses a single generator output via a resistor.
Port-to-Ground
Test Circuit. Port-to-ground and port-to-external-port
testing applies the test voltage longitudinally via the two current-sharing
resistors. The surge voltage is still applied longitudinally in
the port-to-ground circuit, but with a subtle difference from previous
longitudinal port testing. The difference appears at the right side
of Figure 2, where an internal
port is shown being coupled to ground. Previously, equipment, such
as a modem, was not stressed between the external line port and
an internal type of port, such as a universal serial bus. The new
arrangement will test for external/internal port voltage withstand
when the primary protector is not fitted.
The
port-to-ground test takes two forms. The first is to test with all
untested ports powered or terminated. The second is to test, in
turn, with each type of internal port grounded via a coupling element.
Port-to-External-Port
Test Circuit. This type of test is particularly suitable
for power-fed repeaters, which are series devices in which the primary
protector grounding may not be effective. All untested ports are
powered or terminated. Each type of external port is coupled to
ground in turn, including, if present, a port of the same type as
the one being surged. Equipment that has only one external port
type is tested between ports.
At
the basic test level, the port-to-external-port test does not apply
to K.45 and K.21 equipment designed to be always connected to ground.
Port-to-external-port testing does not apply to K.20 equipment unless
an enhanced requirement is specified for telecommunications center
locations with fewer than 250 lines. In that case, such a test is
applied using the K.20 enhanced test voltage levels.
Multiple-Port
Test Circuits. Only port-to-ground and port-to-external-port
configurations are used in multiple-external-port testing. Test
circuits are those depicted in Figures 2 and 3 but with additional
generator feed resistors to connect the multiple ports. For 10/700
testing (recommendation tests 2.1.3 and 2.1.4), the extra loading
will reduce the tested-port stress below the level of single-port
testing.
Single- and Multiple-Port 8/20 Current Testing
Port-to-ground
and port-to-external-port tests for single (test 2.1.5) and multiple
(test 2.1.6) ports are performed on equipment that contains high-current-carrying
protectors that remove the need for primary protection. Despite
modifications, flaws remain in these enigmatic tests.
The
single-output 8/20 current generator does not promote current sharing,
as the generator external-current-limiting resistor is zero. Any
current sharing depends on the coupling element, the test lead length,
and the equipment protection circuitry. Recommendation K.44 warns:
When applying the test to multiple wires, care should be taken to
ensure that the current is divided equally between the wires. Particular
care should be taken to ensure that the operation of one or more
protectors does not prevent the operation of the other protectors.
However,
practical solutions to promote current sharing are not given.
Intuition
suggests that the test lead inductance would help with sharing.
However, laboratory testing with 1-m lead lengths on a single port
with GDT protectors resulted in only one instance of current sharing
in 10 tests. In the remaining nine tests one or another of the wire
protectors operated first and monopolized all the current. Failure
of current coordination limits the total current-test current to
that of a single wire.
The
cause of this problem is the single-output 8/20 high-current generator.
Such 8/20-waveshape generators are widely available and used to
benchmark GDTs, MOVs, and primary protector overstress performance.
Their association with the test term lightning current
perpetuates a common myth: the 8/20 waveshape has nothing to do
with the normal characteristics of real lightning.10
Recommendation
K.44 mandates that primary-protector characteristics comply with
Recommendations K.12 for GDTs11 or K.28 for semiconductor arresters.12
K.28 thyristors have life ratings of 100 applications of 100 A,
10/1000, and must fail low-resistance at 5 kA, 8/20. K.12 GDTs have
life ratings of 300 applications of 100 A, 10/1000, and are supposed
to survive 10 applications of 10 kA, 8/20. Obviously, these 8/20
current tests are created for K.12-type primaries and exclude K.28-type
primaries. U.S. experience has been that 100-A, 10/1000 thyristor
primary protectors are reliable in central offices, but that these
protectors are likely to fail the basic-level 8/20 test of 1 kA.
It is a pity that the testing of integrated GDT primary equipment
is included before the completion of the generic test options.
To
evaluate the overstress caused by near strikes of lightning, primary
protector assemblies are tested at 8/20 wire current levels of 5
kA and 10 kA. Assemblies are mandated not to show external damage.
The absence of a let-through measurement is a major omission in
these tests. In practice, a single measurement cannot capture the
different equipment sensitivities; the most secure approach is to
test the combination of primary protector and equipment. Converting
the high-current 8/20 equipment testing to evaluation of primary/equipment
failure coordination would improve system integrity. The requirement
is that damage not occur to equipment using an external primary.
Damage can occur to equipment with an integrated primary, but hazards
shall not be caused.
Internal-Port Test Circuits
Recommendation
tests 7.1 and 7.2 cover only lightning-induced voltages, whereas
the internal-port tests of GR-1089-CORE cover both lightning and
ac power fault conditions.13 The test circuit to be used depends
on the internal cabling. Figure 4 shows the test circuit for ports
with unshielded cabling. Some untested ports of each type are powered
or terminated during testing, with the unused ports left floating.
 |
| Figure
4. Unshielded-cable longitudinal test circuit, single internal
port. R = resistor, G = ground terminal. |
An
8/20,1.2/50 combination impulse generator is used for unshielded
cable testing with series resistance of 10 (omega). The resistor
changes the wire short-circuit current waveshape from 8/20 to 3.3/30
(see Figure 5) for a 5-(omega) load. Any equipment input resistance
moves the current waveshape further toward the open-circuit voltage
waveshape of 1.2/50.
Ports
with shielded cabling are tested in a multiple-port configuration
with cables and shield bonded at the generator end of the cable
(see Figure 6). An 8/20,1.2/50 combination impulse generator is
used for shielded cable testing with series resistance of zero.
Internal-port tests do not apply to K.45 equipment.
 |
| Figure
5. Combination generator current waveshape variation with external
load. |
Coordination
The
coordination requirement of primary (if fitted) conduction at the
highest test-voltage level remains the same (recommendation test
2.1.2). Changes to Appendix 1 of K.44 have removed the coordination
figure errors that have been reported.5 The line-card example now
used has symmetrical protection voltage levels, which is not so
informative as the previous asymmetrical case. In the rest of the
discussion in this section, the primary and secondary protection
is assumed to be a switching-type protector such as a GDT or thyristor.
Manufacturers
of general-purpose equipment have had a major coordination-testing
problem because they do not know what kind of primary protector
will be used with their equipment. This issue of the resistibility
recommendation as of now misses the opportunity to fix the problem
by specifying a default primary protector as was done with GR-1089-CORE
Issue 3.
 |
| Figure
6. Shielded-cable test circuit, multiple internal ports. R =
resistor, G = ground terminal. |
Adding
the port-to-external-port test arrangement increases the lightning
coordination tests from two to three. The coordination mechanism
for the port-to-external-port test depends on the port impedance
to the equipment ground terminal. For high-impedance ports, the
only high-current (nonflashover) path is through the port primary
protector. Because the port and external-port primary protectors
are in series, the generator voltage for coordination is going to
be above the combined primary-protection voltages. The generator
coordination voltage may be reduced if there are capacitance differences
between the port/protector combinations.
Figure
7 shows equipment in which the two ports connect via low-impedance
coordination elements and conducting secondary protection. As the
impulse voltage increases, if a section of protector P1 operates,
it will cause a voltage jump in the equipment ground terminal. This
voltage increase should cause conduction of a section of protector
P2. Similarly, first conduction of a section of protector P2 will
cause conduction of a section of protector P1. In either case, once
conduction to ground occurs, the test becomes port-to-ground coordination
Note
that only protector P1 needs to coordinate with the equipment. To
have protector P2 coordinate with the equipment, a current-sharing
resistor, as present on the protector P1 side in the figure, needs
to be added to each ground return coupling element. Omission of
these extra current-sharing resistors looks like a test oversight,
as one would expect the circuit to be symmetrical about the equipment
ground terminal. Lack of coordination means that the current rating
of a protector P2 section can be exceeded, because it carries the
total current conducted by both sections of protector P1.
Multiple-port
testing (recommendation test 2.1.4b) further increases the return
current. Including current-sharing resistors for protector P2 and
using the same number of ground return ports as tested ports will
prevent excessive section current.
The
table in Figure 7 gives the
minimum coordination-element resistance for 400-V primary protectors
at three voltage levels. For the port-to-ground coordination, the
coordination resistance has to develop 400 V across the nonconducting
section of protector P1 after the first section conducts. For port-to-external-port
coordination, the coordination resistance has to develop 800 V across
the series-connected nonconducting primaries. These coordination
resistance values converge at higher voltage levels.
AC
Tests
Apart
from the addition of the port-to-external-port test, which increases
the number of configurations from two to three, the equipment resistibility
recommendation updates make little change in the three test categories
of induction, induction with fitted primary, and power contact.
The port-to-external-port ac power fault testing does not apply
to K.20 equipment. K.44 has the 320-(omega) power contact source
resistance error corrected to the 300-(omega) value used in the
equipment recommendations.
One
anomaly is that the power contact source resistance values do not
change for different values of ac mains voltage (test 2.3.1). On
230-V rms mains and with the lowest source resistance of 10 (omega),
the prospective current is 23 A rms. On 120-V rms mains, the prospective
current is down to 12 A rms, yet established testing for GR-1089-CORE
and UL 60950 uses a maximum current of 25 A rms.13,14 There is a
case, based on existing 120-V rms test practice and symmetric-pair
wire gauge conformity, for expressing power cross testing in terms
of a prospective fault current range of 0.25-25 A rms rather than
a source resistance range of 10 (omega)-1 k(omega).
Test Levels
The
designation of test levels as basic and enhanced remains. As before,
Appendix 1 of K.44 discusses higher lightning test voltages for
certain applications. K.21 equipment used in customer-premises locations
with poor primary protection merits extension of the inherent testing
voltage up to 5 kV, 10/700. To encompass field measurements that
show that peak voltages over 7 kV exist, coordination testing up
to 10 kV is allowed.
Test Tables
Tables
I, II, and III
summarize, respectively, the external-port lightning tests,
external-port ac power fault tests, and internal-port lightning
tests defined in the prepublished new recommendations for symmetric-pair
cables. The central portion of each table shows basic and enhanced
test levels for the K.20, K.45, and K.21 recommendations. Blocked
together are tests with the same values, in order to display commonalities
and differences between these three recommendations. Right-hand
columns show the primary protection used and the acceptance criterion
A (withstand without damage) or B (the equipment, although damaged,
shall not cause a fire hazard). Left-hand columns indicate the number
of ports tested and test waveshape, and include notes, test applications,
the test reference number, and the test type.
Conclusion
These
prepublications cover internal and external symmetric pair cable
ports, dedicated power feeds, and mains power ports, leaving coverage
of coaxial ports for future revisions. Integration of other ITU-T
Recommendations increases the equipment and port coverage. With
the increase in breadth comes complexity. The aim of this article
is to give an understanding of the interrelationships of the recommendations
and the test intent.
By
far the biggest problem with the 2000 Recommendations was coordination.
Missed, in this revision, was the opportunity to define a default
primary protector to solve the problem. Table 7 in the K.20 and
K.21 prepublications has the wrong K.44 Figure 6 references.
For
tests 7.1, 7.2, 7.3, and 7.4, the correct figure references are
A.6.5-1/K.44, A.6.5-2/K.44, A.6.3-2/K.44, and A.6.3-1a/K.44, respectively.
Content change is likely before final publication and the most-up-to
date information will be at http://itu.int/ITU-T.
References
01.
ITU-T Recommendation K.20, "Resistibility of telecommunication
equipment installed in a telecommunications centre to overvoltages
and overcurrents" (Geneva: International Telecommunication
Union, July 2003).
02.
ITU-T Recommendation K.21, "Resistibility of telecommunication
equipment installed in customer premises to overvoltages and overcurrents"
(Geneva: International Telecommunication Union, July 2003).
03.
ITU-T Recommendation K.44, "Resistibility tests for telecommunication
equipment exposed to overvoltages and overcurrents--basic recommendation"
(Geneva: International Telecommunication Union, July 2003).
04.
ITU-T Recommendation K.45, "Resistibility of telecommunication
equipment installed in the access and trunk networks to overvoltages
and overcurrents" (Geneva: International Telecommunication
Union, July 2003).
05.
Mick J Maytum, "The New ITU-T Telecommunication Equipment Resistibility
Recommendations," Compliance Engineering 19, no. 1
(2002): 30-37; available from Internet: www.ce-mag.com/archive/02/01/Maytum.html.
06.
ITU-T Recommendation K.15, "Protection of remote-feeding systems
and line repeaters against lightning and interference from neighbouring
electricity lines" (Geneva: International Telecommunication
Union, 1988).
07.
ITU-T Recommendation K.17, "Tests on power-fed repeaters using
solid-state devices in order to check the arrangements for protection
from external interference" (Geneva: International Telecommunication
Union, 1988).
08.
ITU-T Recommendation K.22, "Overvoltage resistibility of equipment
connected to an ISDN T/S bus" (Geneva: International Telecommunication
Union, 1995).
09.
ITU-T Recommendation K.41, "Resistibility of internal interfaces
of telecommunication centres to surge overvoltages" (Geneva:
International Telecommunication Union, 1998).
10.
IEC 61024-1-1, "Protection of structures against lightning,
Part 1: General principles, Section 1: Guide A--Selection of protection
levels for lightning protection systems" (Geneva: International
Electrotechnical Commission, 1993).
11.
ITU-T Recommendation K.12, "Characteristics of gas discharge
tubes for the protection of telecommunications installations"
(Geneva: International Telecommunication Union, 2000).
12.
ITU-T Recommendation K.28, "Characteristics of semiconductor
arrester assemblies for the protection of telecommunications installations"
(Geneva: International Telecommunication Union, 1993).
13.
Telcordia Technologies Generic Requirements, GR-1089-CORE, Issue
3, "Electromagnetic Compatibility and Electrical Safety--Generic
Criteria for Network Telecommunications Equipment" (October
2002).
14.
UL 60950-1, "Information Technology Equipment--Safety--Part
1: General Requirements" (April 2003).
Mick J. Maytum is the telecommunications standards specialist
at Bourns Ltd. (Bedford, UK). He can be contacted via e-mail at
mick.maytum@bourns.com.
|