Part
1 of this article gave an overview of the GR-1089-CORE section
changes and detailed the lightning tests. This second part covers
the ac power fault testing. The degree of change in the standard
merits a whole article focused on the topic. Harmonization with
other U.S. and international standards was a large factor in the
changes, but the standard accounts for legacy equipment performance.
General
As with the lightning tests, the test sample size is three telecommunications
port samples. The new four-wire interface type-A test requires
an ac generator with four separate outputs.
|
Test
|
Open-Circuit
Voltage (V rms)
|
Short-Circuit
Current (A rms)
|
Source
Resistance (W)
|
Duration
(sec)
|
i2t
(A2s)
|
Application
(sec)
|
Primary
Fitted?
|
Connection
Type
|
|
1
|
50
|
0.33
|
150
|
90
|
|
1
|
No
|
Longitudinal
& Transverse
|
|
2
|
100
|
0.17
|
588
|
900
|
|
1
|
No
|
Longitudinal
& Transverse
|
|
3
|
200/400/600
|
1
@ 600 V
|
600
|
1
|
1
|
60
|
No
|
Longitudinal
& Transverse
|
|
4
|
1000
|
1
|
1000
|
1
|
1
|
60
|
Yes
|
Longitudinal
|
|
5
|
Induction
test circuit same as previous issue.
|
5
|
|
60
|
No
|
Differential
|
|
6
|
600
|
0.5
|
1200
|
30
|
7.5
|
1
|
No
|
Longitudinal
& Transverse
|
|
7
|
440
(600)
|
2.2
|
200
(270)
|
2
|
10
|
5
|
No
|
Longitudinal
& Transverse
|
|
8
|
600
|
3
|
200
|
1.1
(1)
|
10
(9)
|
5
|
No
|
Longitudinal
& Transverse
|
|
9
|
1000
|
5
|
200
|
0.4
(0.5)
|
10(12.5)
|
5
|
Yes
|
Longitudinal
|
|
Note:
Figures in parentheses are the previous-issue values
that have changed
|
|
| Table
I. First-level ac power fault test conditions. |
Power
Fault Testing
First-Level
AC Power Fault Tests (Telecommunications Port). Three changes
were made to the tests: objectives becoming requirements, harmonization
to the ITU-T recommendations, and limiter threshold testing. Table
I shows the test conditions. Tests 6 through 9 have been changed
from objectives to requirements, which means that the equipment
must work after these tests. This change represents an increased
requirement for interrupting current limiters such as fuses and
thick-film line feed resistors (LFRs.) Figures 1 and 2 show the
previous and new requirements for current-limiter resistance values
of 50 W, 10 W, and 0.
 |
| Figure
1. Previous first-level ac survival. Previous first-level
ac requirements and current limiter resistance.
|
The
current values are maximum values, calculated assuming that the
current-limiter resistance is the equipment resistance. Previously,
the current interrupter could not operate at about 1 A, 1 second
(1 A2s). Now the most stressful condition is about
5 A, 0.4 second (10 A2s). Many existing LFRs may not
be able to meet the new requirement, necessitating the inclusion
of a resettable current limiter, such as a positive-temperature-coefficient
(PTC) thermistor. A PTC thermistor reduces the current, avoiding
LFR fracture and permanent current interruption.
Harmonization
with ITU-T recommendations is shown in Table I by the figures
in parentheses. Three harmonization methods are used: voltage
change (test 7), source resistance change (test 7), and time change
(tests 8 and 9). The changes to tests 7, 8, and 9 match the enhanced
level conditions of the ITU-T power induction test 2.2.2 with
an i2t value of 10 A2s, with a source resistance
of 200 W.
Compared
with the previous i2t conditions of tests 7 through
9, test 7 is the same, test 8 is increased by 11%, and test 9
is reduced by 20%. Tests 3 and 4 already correspond to the 1-A2s
test condition of the basic level conditions of the ITU-T power
induction test 2.2.2.
 |
| Figure
2. New first-level ac survival. New first-level ac requirements
and current limiter resistance. |
In
Figures 1 and 2, test 3 generator levels are 600 V rms and 1 A
rms. Note 6 says that test 4 generator levels are set to 1000
V rms and 1 A rms to operate the added primary protector. Note
6 is unchanged from the previous issue and continues to neglect
the equipment resistance loading on the generator. The default
600-V rms carbon-block primary protector operates only when the
equipment load impedance develops at least 600 V rms. For the
test 4 generator source resistance of 1000 W, the equipment
resistance must be more than 1000 X 600/(1000 600) = 1500
W. However, many pieces of equipment will have impedances
below 1500 W, so the test objective of primary operation
is not fulfilled.
First-level
threshold testing of the equipment current and voltage limiters
is now done with the resettable current limiter bypassed and the
overvoltage limiter removed. The advantage to this new approach
is that the circuits following the limiters are now stressed to
the worst-case-condition voltage and current rather than to the
values of the fitted limiters. As explained in the first part
of this article, threshold means the limiter maximum let through,
which in this case is under ac conditions.
For
the voltage limiter, the maximum limited voltage value needs to
be identified. The generator open-circuit voltage is then set
to this level and applied to the port with the limiter removed.
For example, a TISP4350H3BJ thyristor voltage limiter has a typical
ac protection voltage of ±310 V and a maximum guaranteed
value of ±350 V. Under test, this protector would be removed
and a 350-V peak, 248-V rms ac generator applied to the port.
This test may apply up to 40 V more than the typical protector
would allow, and this increases the confidence in the equipment
withstand, in spite of the small number of samples used.
 |
| Figure
3. Asymmetrical voltage-limiter threshold testing. Sinusoidal
waveforms with +2.5 V peak and 56.6 V peak. |
Certain
applications have asymmetrical limiting voltages, and the positive
and negative peak voltages will be different. In Part 1 of this
article, a TISP61089B gated limiter had example values of +2.5
V and 56.5 V. Obviously, generating a 60-Hz ac sine wave
of +2.5 V peak and 56.5 V peak is not straightforward. Separate
test runs of half sine waves of +2.5 V peak and 56.5 V peak
is the easiest solution, but this approach results in less heating
than simultaneous application of a +2.5-V-peak and a 56.5-V-peak
waveform. More-complex solutions could entail a 59-V peak-to-peak
(2.5 V + 56.5 V) sine wave biased by a 27-V dc (59
V/2 + 2.5) source or by using electronic switches to switch in
an appropriate ac source voltage in each polarity (see Figure
3).
Self-resettable
current limiters will operate in some tests and reduce the test
current. In such cases, the current limiter is bypassed, and the
limiter maximum operating threshold current is applied to the
port. PTC thermistors are the most common form of self-resettable
current limiters, and these respond to rms current.
Testing
should apply an rms current equal to the maximum trip current
of the PTC thermistor. Asymmetrical voltage limiters complicate
testing because the resulting circuit current could be asymmetrical.
However, modern digital oscilloscopes can automatically calculate
the rms value of a waveform, allowing the correct rms current
value to be set.
Telecommunications
Port
 |
| Figure
4. Comparison of old and new equipment current limits. |
Current-Limiting
Protector Tests for Non-Customer-Premises Equipment. Digital
services equipment, operating at bit rates higher than 1.544 Mb/second
or 1.1 MHz, have two new conditional requirements. Digital services
equipment should not require an external current limiter. If the
equipment does need an external current limiter, then the limiter
must comply with the GR-974-CORE digital requirements.
Two
new current-limit indicators have been added. To harmonize with
UL 60950, the use of an MDL 2.0-A fuse is now allowed as well
as the previously allowed MDQ 16/10-A
fuse. In recognition of modern digital oscilloscope waveform capture
capabilities, noninvasive current measurement using a current
probe is now acceptable to determine the performance of the equipment
current limiter.
Under
test, the equipment shall not create a safety hazard or operate
any current-limit indicator fuse. The maximum equipment current-time
limits are indicated by the green line in Figure 4. For comparison,
the previous limit values are shown by the red line in Figure
4. The equipment must now reduce or interrupt the current earlier
in the 350-second time range. However, the current is allowed
to pass nearly 3 A long term compared with the previous 2 A.
 |
| Figure
5. MDQ and MDL fuse comparison. |
This
long-term increase has occurred due to legacy equipment considerations,
adoption of the UL 60950 MDL 2.0-A fuse, and a blind spot created
by the previous ac test generator arrangement. Figure 5 shows
the published curves for the MDL 2.0-A and MDQ 16/10-A
fuses.
The
MDQ is a double-element fuse, and this gives the step in the 0.52-second
region. Being a single-element fuse, the MDL has a smooth curve.
Comparing these curves to those in Figure 4 shows the equipment
limit curve previously used was based on the MDQ 16/10-A
fuse characteristic, and the new limit curve is based on the MDL
2.0-A fuse characteristic. Figure 5 also shows the MDL 2.0-A fuse
maximum limit of 120 seconds at 4 A. Typically, the fuse will
operate at 120 seconds with only 2 A flowing. This 4-A maximum
to 2-A typical current-indicator spread shows how inaccurate,
and hence inappropriate, the use of commercial fuses can be. Fortunately,
modern digital measurements can preclude the use of fuse indicators.
| Short-Circuit
Current (A rms) |
Maximum
Duration at Current ValueFigure 4 (Green) Wiring Simulator
(sec) |
Maximum
Duration at Current Value26 AWG Wiring Simulators (one
sample) (sec) |
| 2.2 |
Unlimited
(see note) |
Unlimited
(see note) |
| 2.6 |
Unlimited
(see note) |
Unlimited
(see note) |
| 3.0 |
900 |
Unlimited
(see note) |
| 3.75 |
20 |
Unlimited
(see note) |
| 5 |
6.8 |
Unlimited
(see note) |
| 7 |
2.5 |
Unlimited
(see note) |
| 10 |
0.94 |
900 |
| 12.5 |
0.53 |
19 |
| 20 |
0.17 |
3.8 |
| 25 |
0.099 |
2.4 |
| 30 |
0.065 |
1.8 |
|
Note:
Current limiter indicators are not required to be
fitted.
|
|
| Table
II. Equipment current-limiting protector test currents. |
The
30-A ac test generator has been changed from a 20-W, variable-voltage
source to a fixed 600-V rms source, variable resistance. This
change was implemented to avoid the blind spot created by the
original generator. In many cases, the equipment input circuit
can be simplified to a current and voltage limiter. In Figure
6, these limiters are shown as a fuse current limiter and a thyristor
voltage limiter. The prospective short-circuit current can only
flow once the thyristor has switched into a low-voltage state.
 |
| Figure
6. Simplified generator and equipment circuit. |
To
cause this switch, the generator voltage must exceed the voltage-limiting
level of the thyristor. Below this voltage level, current flow
is impossible. Use of the original 20-W variable voltage
source generator prevented equipment testing down to 2 A rms for
voltage limiters of 80 V and above. For example, a 200-V limiter
would prevent testing below 5 A rms (assumes switching at generator
voltage peak, so that current flows for only 50% of the half-cycle).
Changing to a 600-V rms source, variable-resistance generator
fixes this current-range-truncation problem. The default primary
let-through voltage is 600 V rms, so it is puzzling that a 600-V
rms source, variable-resistance generator was not used in the
first place (see Figure 7).
The
specific generator-current levels that the equipment must be tested
to are shown in Table II. Two test-current levels (2.2 A rms and
2.6 A rms) are in the acceptable region and, therefore, do not
require the wiring simulator to be fitted. These current levels
are 15-minute hazard tests, and it is not important whether the
equipment current limiter operates.
|
Test
|
Open-Circuit
Voltage (V rms)
|
Short-Circuit
Current (A rms)
|
Source
Resistance (W)
|
Duration
(sec)
|
i2t
(A2s)
|
Connection
Type
|
|
1
|
120,
270
|
25
|
4.8,
11
|
900
|
|
Longitudinal
&Transverse
|
|
2
|
600
|
60
|
10
|
5
|
18,000
|
Longitudinal
& Transverse
|
|
3
|
600
|
7
|
86
|
5
|
245
|
Longitudinal
& Transverse
|
|
4
|
100600
|
2.2
@ 600 V
|
270
|
900
|
|
Longitudinal
&Transverse
|
|
5
|
Induction
test circuit same as previous issue.
|
900
|
|
Differential
|
|
| Table
III. First-level ac power fault test conditions. |
The
2.2-A rms test level is the lowest unacceptable current retained
from the previous issue for legacy purposes. Testing at the 2.2-A
rms level duplicates the 2.2-A rms second-level ac power fault
test 4, and so the results from test 4 can be used. The 2.6-A
rms test level is midway between the 2.2-A rms level and the new
lowest unacceptable current level of 3.0 A rms. Its purpose is
to test for any hazard that might be missed by just testing at
the 2.2- and 3.0-A rms current levels (blind spot avoidance).
Current-Limiting
Protector Tests for Customer-Premises Equipment. Tests are
performed using a wiring simulator, which differs depending on
the means of connection to the outside plant. Equipment connected
with premises-type wiring must be tested as in the previous section.
For equipment that is directly connected with cable, the wiring
simulator must be a 30-cm length of 26 AWG copper wire draped
in cheesecloth. Figure 8 shows some laboratory current-time measurements
of a 26-AWG-wire simulator. Compared with the customer-premises
wiring simulator, the cable simulator allows about three to four
times the current flow, enabling use of higher-current-rating
fusible limiters. The hazard tests now extend to 7 A rms, and
whether the equipment current limiter operates is not important.
 |
| Figure
8. A 30-cm, 26 AWG wiring simulator (red line). |
Second-Level
AC Power Fault Tests. Non-customer-premises equipment and
customer-premises equipment have the same tests. Table III shows
the test conditions, which haven't changed from the previous issue
of the standard. Again, equipment-limiter threshold testing is
done by removing the voltage limiter and bypassing the current
limiter. One difference in the bypassed-current-limiter test is
that the limiters can be resettable or nonresettable (e.g., fuses).
Only
first-level tests consider resettable current limiters because
the equipment must work after testing. For first-level testing,
the current is set to the maximum current that would not be interrupted
by the current limiter within a 15-minute period. Comprehending
both resettable and nonresettable limiters, second-level testing
sets the available current value to the maximum operating threshold
of the current limiting device. This test current is the maximum
current that would not be interrupted or reduced by the specified
current limiter within the test duration (5 or 900 seconds). Unfortunately,
the test note goes on to say, "The maximum operating threshold
for a current-limiting device is 135% of the rated current," without
qualifying, as in the previous issue, that this threshold applied
only to fuses.
 |
| Figure
8. A 30-cm, 26 AWG wiring simulator (red line). |
Equipment
using resettable current limiters should be tested with a current
equal to the maximum trip current for the test duration. However,
people could misinterpret the maximum trip current as rated current.
Using a current 1.35 times the highest trip current will overstress
the equipment compared with the actual worst-case condition. The
1.35 factor comes from UL 248, which, for standard fuses up to
30 A, specifies that the fuse must operate within 60 minutes at
1.35 times the rated current. However, the fuses used in telecommunications
port interfaces must withstand lightning tests and are usually
surge-withstand fuses. Microfuse (10-mm) versions of these special
fuses do not comply with the 1.35 factor, and a 1.25-A-rated fuse
is often designed not to interrupt the current in 2.2-A rms testing.
This fuse has a 2.2/1.25 = 1.6 factor. Testing with 1.35 times
the rated current (1.7 A rms) will understress the equipment compared
with the actual worst-case condition.
Conclusion
The changes to the previous ac tests are subtle rather than major.
However, these changes will drive different testing procedures,
component improvement, and more-rigorous circuit design.
Mick
J. Maytum is applications manager for Bourns Ltd. (Bedford, UK).
He can be reached via e-mail at mick.maytum@bourns.com.