Guidance
Note Addresses Surge Test Problems
Tim
Williams and John Flood
A
new guidance note provides advice for dealing with some key issues
that have surfaced with the increasing use of the IEC 61000-4-5
surge test.
The
use of the surge test required by IEC/EN 61000-4-5 is becoming
more commonplace as the newer product and generic standards refer
to it as a matter of course. With this more frequent use, its
shortcomings have become more apparent. The basic standard includes
some requirements that are not well defined and for which the
product standards give no additional guidance.
Some time ago, the EMC Test Laboratories Association (EMCTLA)
published a technical guidance note (TGN 39) addressing one of
the issues. The guidance is in the process of being updated to
cover other issues as they are raised. In addition, IEC subcommittee
(SC) 77B, the International Electrotechnical Commission (IEC)
committee responsible for the standard, is looking at updating
IEC 61000-4-5 in the framework of the normal maintenance cycle.
This update, however, will take several years.
EMCTLA is a grouping of UK EMC test laboratories, organized to
promote the interchange of information on technical and regulatory
issues in EMC testing. Members of the association request guidance
from the appropriate panel via the secretary of the working group.
The panel considers the request, together with any additional
information, and reports to the secretary any guidance to be given.
The panel's recommendations are distributed to members and are
also freely available via the EMCTLA Web site.
Once published, the technical guidance notes (TGNs) are not only
sent to the UK Department of Trade and Industry (DTI), but also
to the European Commission in Brussels. Currently there are 42
TGNs, with further notes in process. Although TGNs are widely
used as a source of guidance within the UK, it should be noted
that they have no legal standing and are not necessarily recognized
across Europe.
Each TGN carries a legal disclaimer. They are not intended to
conflict with the instructions in standards, but rather should
offer a particular interpretation whenever necessary. Other countries
that apply CE marking may have different interpretations of some
of the issues raised in a particular guidance note.
TGN 39: Addressing the Issues
This article discusses the issues in the context of the new version
of the EMCTLA TGN and provides some reasoned guidance to address
some of the problems that are being encountered. One particular
product standard, the recently published second edition of IEC
60601-1-2 on medical electrical equipment, does recognize some
of the major problems and attempts to resolve them. This standard
is referenced where relevant. EN 50270, EMC of gas detectors,
is another European product standard that provides a specific
modification to the surge test application.
Applying the Surge Voltage in Increasing Steps. Testing
to IEC/EN 61000-4-5 requires that the disturbing signal be applied
to the equipment under test (EUT) at levels up to and including
the maximum level specified for the apparatus. Clause 8.2 states,
The test procedure shall also consider the non-linear current-voltage
characteristics of the equipment under test. Therefore the test
voltage has to be increased by steps up to the test level specified
in the product standard or test plan. All lower levels including
the selected test level shall be satisfied. For testing the secondary
protection, the output voltage of the generator shall be increased
up to the worst-case voltage breakdown level (let-through level)
of the primary protection.
This statement raises a number of questions. The basic test standard
is nearly always used by reference from a product or generic standard.
It would be open to these standards to give some explicit instructions
as to the choice of levels, but in general they do not provide
any guidance. Therefore, it should be clear that a manufacturer
could not declare compliance based on a test at the compliance
levels only. But, if a manufacturer is required to test in increasing
steps up to the compliance level, what steps should be used? The
basic standard defines severity levels, but it does not explicitly
link these to the required steps. A specific test plan could do
so, but most clients rely on a test house to advise them on a
test plan.
The EMCTLA view is that all lower severity levels as specified
in the standard should be tested up to the maximum specified by
the product committee or test plan. The specified levels are 0.5,
1, 2, and 4 kV and x (special). For products specified to 0.5
kV maximum, a lower level of 250 V may be used to test protection
let-through.
For the higher final-test levels, multiple steps contribute to
an excessively long test, but reliance on testing to the maximum
level alone is not what the standard specifies. IEC 60601-1-2,
ed. 2, has considered the question and places an explicit requirement
on the levels to be tested. The standard specifies that if the
equipment has no surge protection device, then only the highest
levels need be tested. It justifies this requirement as follows:
 |
| Figure
1. The flowchart represents the intended test sequence for
the application of surges. |
The
surge test is mainly a test for the ability of the power supply
to withstand this high-energy pulse. If no surge protection device
is installed ... a test at only the highest immunity test level
specified, ±2kV for ac power lines to ground and ±1
kV for ac power line to line, will be the worst case. In that
case, testing at lower immunity test levels is not useful and
would provide no additional information. If a surge protection
device is installed ..., testing at lower immunity test levels
is necessary to verify proper operation of the surge protection
device.
Although this advice may be helpful to medical device manufacturers,
there is no immediate way to apply such guidance more generally.
A similar specification could be put into other product standards,
and the fact that it hasn't suggests that the authors of those
standards do not see the issue as worthy of their concern.
The TGN states that, when applying tests for CE marking, the maximum
level of surge to be applied should be that given in the product
specific or generic standard. All lower severity levels shall
be tested up to the maximum specified, as IEC 61000-4-5 mandates.
On the other hand, applying additional investigative tests or
examining immunity up to the primary protection level, as is implied
by the first and last sentences of the paragraph quoted above
from IEC 61000-4-5, should be part of the manufacturer's design-proving
work and not part of a compliance test.
Number of Surge Pulses versus Phase Angle. The basic standard
requires at least five positive and five negative tests at the
selected points and, if not otherwise specified, the surges must
be applied in synchronization with the voltage phase at the zero-crossing
and the peak value of the ac voltage wave (positive and negative).
This could be interpreted as requiring either:
- Five
pulses at each of four phase angles (0°, 90°, 180°,
and 270°),
giving a total of 20 pulses for each polarity at each voltage
level; or,
- Five
pulses distributed between each of the four phase angles,
requiring only five pulses for each polarity at each voltage
level; or,
- Some
number in between.
Naturally, the second of these options is most attractive to test
house customers because it requires only a quarter of the time
of the first interpretation, but this option fails to indicate
how the pulses might be distributed in phase. However, the EMCTLA
view is that, for ac power ports (input or output), the surges
shall be applied synchronized to the ac voltage phase at 0°
or at 180°, 90°, and 270°. Product committees may
select different phase angles as appropriate to the product. Although
testing at both 0° and 180° is allowed, testing at only
one zero-crossing point is considered to be necessary.
This interpretation requires a total of 15 pulses for each polarity
at each voltage level. It is consistent with the requirement laid
down explicitly in Clause 36.202.5 of IEC 60601-1-2.
Time between Pulses. The normal minimum period as specified
in the standard is 1 minute, although the standard also states,
"The maximum repetition rate depends on the built-in protection
devices of the EUT." EMCTLA suggests a shorter period may be agreed
between test laboratory and manufacturer, but it also recommends
that this be not less than 20 seconds to avoid undue component
heat stress.
The concerns over the potentially excessive test time and possible
component stress are not fully addressed in this TGN. These are
matters that need consideration at the international level and
may be the subject of a request for new work initiated through
IEC SC 77. The flowchart in Figure 1 represents the intended test
sequence for the application of surges. Exceptions would be noted
in the test plan or test report, with reasons for departure.
Set-up for Tests Applied to Shielded Lines. There are other
difficulties with the standard that are addressed in EMCTLA's
TGN.
Test operators should be aware of a possible safety hazard when
applying surges to shielded cables in accordance with Clause 7.5
(Figures 13 and 14 of the standard). Figure 2 illustrates Figure
13 of the standard. A faulty shield connection, resulting in a
high impedance to the ground reference, could cause a dangerous
charge to build up on the EUT (shown as EUT 1 in the figures).
To ensure the safety of the operator, it may be necessary to allow
discharge of the cabinet between pulses.
This discharge can be achieved by the connection of 2 x
470-kΩ) high-voltage-rated resistors between the chassis
of EUT 1 and the ground reference (similar to the ESD coupling-plane
discharge network). Because the surge generator is not designed
for continuous operation and considering the maximum rate of application
to be 1 pulse per 20 seconds, the resistors can safely be rated
at 0.5 W each. It is unlikely that the high value of resistance
introduced between chassis and ground will have a detrimental
effect upon the waveform of the generator.
 |
| Figure
2. Test operators should be aware of a possible safety hazard
when applying surges to shielded cables in accordance with
Clause 7.5 (Figures 13 and 14 of the standard). This shows
a modified Figure 13 (Figure 14 is similarly modified). |
The
value R* in the test generator output for this screened-cable
interface test is uncertain from the standard (0, 10, or 40 Ω).
Annex B.1 definitions, which state that 42 Ω) applies to
all lines other than low-voltage power supply network lines, appear
to conflict with the wording in Clause 7.5. This clause itself
states, "The test level applied on shields is the 'line-to-earth
value' (2-Ω) impedance)"; in fact, the line-to-earth source
impedance is 12 Ω). It is recommended that until the standard
is more clearly worded, that R* be 0 Ω) (i.e., no additional
resistor), leaving the output impedance of the generator as 2
Ω) (value as given in Clause 7.5).
Clause 7.5 does not clarify where the surge is to be applied.
If a handheld probe is in use, this surge can be applied to the
metalwork of the cabinet. However, this method may limit repeatability.
Suggested guidance is to simulate real-world conditions in which
a surge appears between the grounds of the two interconnected
systems. Therefore, the best way of achieving realistic conditions
and a repeatable test is to apply the surge at the usual earthing
point of the chassis or to a metallic connector shield.
When applying surges in line-to-line mode to a three-phase ac
port, testing can be restricted to the combination, 3C2
(e.g., L1–L2, L1–L3, L2–L3, not L1–L2
and L2–L1, etc.). This restriction is justified because both
polarities are tested on the lines under test.
Figures 6 and 7 in the standard do not clearly differentiate connections
or feedthrough of the L, N, and E wires of the mains supply to
the decoupling network. Test operators should ensure that the
decoupling network case is connected both to protective earth
(PE) and to the test system ground reference as is shown in Figures
8 and 9 in the standard.
The advice given in this article is based on engineering judgment,
comments from sources within EMCTLA, and IEC SC 77B Working Group
11's draft working document. The authors welcome additional comments
that may be used to further improve the published EMCTLA TGN.
The text of the TGN can be found on the EMCTLA's Web site, http://www.emctla.co.uk,
and comments can be made via the secretary, dimeson@iee.org.
Tim Williams is with Elmac Services (West Sussex, UK). John
Flood is with Accent Europe Ltd. (Leicestershire, UK). They are
both members of Working Group C of the EMC Test Laboratories Association,
UK.
|