Pathways and Pitfalls of Product Safety Certification
Andrew
DeIonno
Preparation,
especially knowing and understanding the right standards, is key
to obtaining safety certification.
One
day while pondering a better way to catch a mouse, you think of
an innovation that will revolutionize mouse catching. You bring
the concept to a design house, develop prototypes, do market research,
and you think you are ready to begin producing and selling your
new invention. But you discover that the product needs a safety
certification. You find a lab, submit the product for testing,
and expect a label. But are you prepared for the process?
This
scenario is familiar to anyone who has been involved in the actual
certification process or who has submitted a product to a safety
laboratory. The product safety certification process is complex,
and it requires a great deal of preparation, especially to get
products through a laboratory on the first try. Even with preparation,
there is no guarantee that a product will meet the minimum safety-level
requirements the first time; however, manufacturers that have
done their homework in the early stages of design will be more
likely to avoid traps later in the certification process.
Part
of the process is knowing what standards apply to each unique
design. Some product safety standards, such as those for information
technology equipment (ITE), have multiple-country harmonization.
The ITE standard is based on IEC 60950 and is adapted to each
country by national deviations. For example, the standard in Europe
is EN 60950 (IEC 950 and EU deviations). In the United States,
it is UL 60950. In Canada, it is CSA 22.2 No. 950. Each country
applies its own deviations.
Other
standards follow the same harmonization philosophy. A few additional
categories are outlined in Table I. If a product falls into one
of these broad categories, then global compliance becomes simpler
because of this harmonization. For products that do not fall into
one of these categories, manufacturers must review the standards
for each country where they plan to distribute the product, and
then design it to meet those particular standards. Standards can
vary greatly from country to country.
Being
Prepared
It
is critical to have a general understanding of the product safety
certification process (see Figure 1). The process follows three
general phases: initial engineering review (construction review),
testing, and reporting.
Initial
Engineering Review (Construction Review). A laboratory engineer
evaluates the product against each clause of the appropriate standards.
The engineer will need to determine one of three solutions for
each clause: pass, fail, or not applicable. Pass and not applicable
are straightforward, but when a product fails to meet the minimum
requirements of a clause, manufacturers are faced with possible
redesign and rereview.
 |
|
Figure
1. The product safety certification process and possible pitfalls.
|
Testing.
The laboratory subjects the samples to a battery of tests in the
worst-case normal and abnormal (single-fault) conditions. The required
tests are clearly defined in the body of the standards reviewed.
Reporting.
In this phase, a report is generated that specifies critical features,
components, and construction of the sample. These features are
identified during both the construction review and the testing
phases of the evaluation.
Ensuring
Compliance
The
single best way a manufacturer can help ensure that a product
will comply is to know the requirements of the standard against
which the product will be tested. By reading and understanding
the standards that the laboratory will be using, manufacturers
can avoid problems caused by insufficient design, uncertified
components, and so on.
|
General
Equipment Type
|
IEC
Base
Standard
|
Common
National References
|
|
Medical
equipment
|
IEC
60601-1
|
UL
2601-1, CSA
C22.2 No. 601-1,
EN 60601-1
|
|
Laboratory
equipment
|
IEC
61010-1
|
UL
3101, UL 3111,
UL 3121, CSA
C22.2 No. 1010-1,
EN 61010-1
|
|
Household
and similar
equipment
|
IEC
335-1
|
UL
60335-1,
CSA 22.2
No. 335-1,
EN 60335-1
|
|
|
Table
I. Typical standards that may apply in the product safety
certification process.
|
Manufacturers
need to review the standard as early as possible in the design stage.
It is impossible to learn all of the requirements just a few weeks
before final production or distribution. Without early review of
the standard, manufacturers risk hitting several costly pitfalls.
Common
Design-Stage Pitfalls
Every
stage of the safety certification process has possiblebut avoidablepitfalls.
Designing a product with standards in mind helps avoid unnecessary
costs that can arise in all three phases of the process. Some
of these pitfalls and their associated costs include construction
deficiencies, testing failure, missing information, and guesswork
design.
Construction
or Testing Deficiencies. Costs include time and labor to redesign
because of construction or testing deficiencies, and to retest
and reevaluate the product at the laboratory. Additional costs
that need to be accounted for include lost time to market and
research and development.
Test
Failure. Without knowing the specific tests before submitting
a product to a laboratory, it is impossible to know whether a
product in normal or single-fault mode could lead to a test failure.
Test failures add unexpected costs associated with redesign. For
example, for an electric heat system (whether it is for heating
fluid, gas, or material), a test failure could be caused by flaws
in the design. Prior to lab submission, the following questions
should be answered:
- What
happens if the liquid or gas being heated fails to flow? Can
the heater, in this runaway condition, ignite material?
- If
the heater relies on a fan to remove the heat generated and
the fan fails to operate, could the heater short to ground and
pose a potential electrical shock hazard?
- Could
a restriction on a gas or fluid flow cause the heater to overheat
other adjacent components and pose an ignition or electrical
shock hazard?
A
"yes" to any of these questions will most likely require some
redesign, retesting, and delayed production. But it is important
to note that this is the mindset manufacturers need to have prior
to testing to ensure that they know with reasonable certainty
that no surprises will be discovered during the laboratory testing.
Missing
or Incomplete Information. When manufacturers are familiar with
a standard, they are in a much better position to provide the
necessary information at the onset of a project. They can also
be fairly confident that their product will comply with the construction
and testing requirements called for in a given standard. This
self-audit also helps uncover design deficiencies before submitting
a product for testing and certification.
|
|
|
|
Input
|
Verifies
the manufacturer's product
ratings when operating
under full load.
|
|
Temperature
|
Simulates
worst-case normal full-load
operating condition. It
verifies that component, material,
and ambient temperatures
are not exceeded.
|
|
Dielectric
voltage withstand
|
Verifies
that the insulation systems
between parts of the machine
are sufficient.
|
|
Enclosure
|
Verifies
that the enclosure will
not become damaged to such an
extent as to expose hazards (includes
both electrical and mechanical).
|
|
Abnormal
operation
|
Simulates
likely single-faultconditions
and is intended toshow
that the equipment willnot
pose an increased risk offire,
shock, or mechanicalhazard
when the equipmententers
into the failure mode.
|
|
|
Table
II. Typical tests conducted for product safety certification.
|
Guesswork
Design. Most importantly, try to avoid design and testing by trial
and error. Manufacturers that understand the standards also understand
a laboratory's comments and reports. Deficiencies are more often
minimal and can be corrected through a single iteration.
Construction
Review
Manufacturers
that successfully pass the construction review the first time
have usually reviewed the standards and know that their product
will pass all applicable construction requirements. To ensure
that the laboratory follows the same interpretations as the manufacturer,
a submission should contain a road map through the standard. A
road map provides the supporting engineering documentation showing
compliance with each clause in the standards referred to during
design. This documentation varies from standard to standard, but
it usually includes installation, operation, and maintenance manuals;
detailed schematics; critical-component cut sheets and supporting
certification information; all required labeling (for the product);
and any other information appropriate to show compliance with
a particular clause. During construction review, three key pitfalls
can arise:
- Design
Failure. The design fails to meet the constructional requirements.
Costly redesign could be required.
- Missing
Information. Not all of the information is supplied. Omitting
critical information at this stage could lead to costly delays
or additional component testing. Manufacturers should review
and supply the laboratory with the conditions of acceptability
for all components to ensure that each component meets these
requirements in the end product design prior to product submission.
If a component has conditions that need to be met in the final
(end) product, then it will have conditions of acceptability.
The conditions are available from the component manufacturer.
- Incorrect
Components. Costly project delays can result from incorrect
components, missing information, or components that have not
been evaluated for the application used in the design.
Testing
Similar
to the construction review phase, it is essential that manufacturers
are confident that their products meet the required tests before
submitting them to the laboratory. Some examples of common tests
are listed in Table II. Testing failures lead to costly design
changes and subsequent retesting. If the cause of the failure
is difficult to identify, manufacturers could find themselves
back at the design stage. The testing phase presents many pitfalls,
most of which can be avoided. Two critical testing pitfalls include:
- Single-Fault
Testing. Try to anticipate as many of the single-fault tests
(and simulate them) before submitting a product to a laboratory.
In addition, discuss the test program with the laboratory engineer
before testing begins. In some cases, a laboratory may be planning
a test that was not anticipated during the design phase of the
product. Don't gamble on a product passing. The costs are usually
too great (redesign, retesting, and lost time to market). Have
a high degree of confidence that the design meets the tests
required in the appropriate standards.
- Component
Testing. Evaluation of specific components may not be included
in the laboratory's quoted cost. It is important to know whether
related testing, such as testing of transformer faults and motor
faults, is included in the laboratory's estimate. It is also
important to review the component certification information
to know whether testing was performed during the component certification.
Be sure to include this information in the documentation provided
to the laboratory.
Reporting
Manufacturers
that have done their homework for the construction review and
testing phases will have all of the information necessary to generate
a comprehensive report. When manufacturers fail to prepare properly,
deficiencies and problems are often discovered only when the laboratory
notifies them through test-failure reports or a construction review
letter.
If
manufacturers do their homework, then all the laboratory needs
to do is issue the final test or certification report showing
all of the critical features of the product from both the construction
review and testing.
Conclusion
With
some planning and preparation, manufacturers can save valuable
time and money in the certification process. When manufacturers
understand the certification process and provide the information
required for the laboratory to perform the job, the process flows
smoothly. Manufacturers can avoid the pitfalls by understanding
the pathwaysthe processand knowing the rulesthe standards.
When manufacturers have studied the standards and designed with
them in mind, a product is much more likely to make it through
the process successfully.
Andrew
DeIonno was formerly senior engineer for MET Laboratories (Morrisville,
NC). He can be reached via e-mail at ddeionno@earthlink.net.
|